NewsTop Stories

Revealed :Chamisa trashes Biti’s ‘false’ claims over Augur airport road deal


Harare- IT has emerged that CITIZEN COALITION for Change (CCC) leader Nelson Chamisa backed the Augur Investment Airport and Mbudzi mall deal that his acolyte Tendai Biti has vehemently castigated om court during his assault case ,where he allegedly assaulted a female investor whom he linked to Augur .

His submissions were however thrown in the dust bin by Deputy Prosecutor General Michael Reza, who deemed same ” irrelevant” to the assault matter at hand.

On Wednesday, Augur Investment director Michael Van VAN Blerk spoke out about his company’s legitimacy.

Express Mail Zim presents hereunder his full statement

” I would like to correct the record as best I can.

” This misinformation campaign has been largely expressed on underground media platforms, driven by people desperate to avoid accountability. “Some articles have also been featured in the press, informed by dishonest sources.
” My suspicion is that defendants accused of wrongdoing against Augur and its employees are using these false statements to evade responsibility before Zimbabwe’s legitimate courts.

”  I have set out this clarification on my own free will without any coercion or request from Augur or anyone else and without having met the lawyers nor having seen the Fairclot Court trial documents.

 

 

” In 2008, Augur Investments OU and the City of Harare formed a joint venture for the Sunshine land development project. Zimbabwean staff were recruited for this work, which included Mbudzi People’s Market, a 6000 square meter covered market, amongst other projects.

“The government approved this joint venture, and in 2009, Augur registered as a foreign investor with the Ministry of Justice.

” This JV invited Augur to plan, design, and construct the Airport Highway.

“As the Airport Highway is a national road, Augur and the COH were required to obtain government approval in order for Augur to construct it.

“One of the largest road construction companies in Southern Africa, Power Roads, priced the project independently.

“The recently built Ngezi Road which was finished with chip and spray tarmac inferior to the asphalt finish of the Airport High way, was compared to the Airport Highway, and found to be more expensive despite the cheaper chip and spray product. “Augur’s price for asphalt per running meter was considerably lower.  The plan was approved by the President and Cabinet after being presented to Government.

“The Ministry of Transport and the Ministry of Local Government were designated as Government supervisors by Cabinet with final approval received from the Ministry of Finance.

” Due to the municipality’s @inability to make cash payments, 90% of Augur’s payment was offered in the form of land instead of cash. The government supported this initiative and contributed additional land to the project in order to aid the COH.

“This was reduced to a legally binding contract signed by both parties.  Before land tranches were paid out to Augur, the Zimbabwean-hired design engineers, Ministry of Transport engineers, COH engineers, and Ministry of Local Government engineers were responsible for reviewing and approving the work and progress certificates/invoices.

“To facilitate this payment process, Augur formed a number of Zimbabwean landholding corporations and received RBZ approval for these Zimbabwean landholding corporations and their offshore shareholding.

” Only after official and approved progress payment certification by the three governing entities would land be released.  Augur recruited Fairclot, a local company, as a subcontractor under its direct supervision. Fairclot was not the entity responsible for construction, but rather a subcontractor.

”  In exchange for its services, Fairclot initially agreed to accept a 25% cash payment and a 75% land payment. This land payment portion could only be made after delivery of title from the COH. Fairclot breached these original contractual terms, and demanded a revision to a 40% cash payment and 60% land payment. Augur paid Fairclot 40% of the invoiced amounts in cash, close to USD 4 million in amount, with the remaining 60% to be paid in land.

” The operational incompetence of the COH resulted in massive delays at Augur’s expense, impeding work from beginning to end. Augur suffered the brunt of delay-related expenses. The City of Harare then attempted illegally to terminate the valid contract, resulting in arbitration, which Augur, represented by Advocate Nelson Chamisa, ultimately won.  The arbitration and subsequent court award mandated that Augur be compensated with a parcel of government-owned land whose title was held by a law firm with which Augur had a close working relationship. Tragically, the appointed partner of this firm had died, disrupting the flow of information at the law firm, and the title deed was not delivered to Augur. Resolution was affected with the intervention of the Sheriff of the court.  Following the successful arbitration Fairclot was offered a land parcel as settlement.”

Related Articles

5 Comments

  1. Every weekend i used to visit this web page, as i wish for enjoyment, since this this website conations
    in fact good funny stuff too.

  2. It’s very straightforward to find out any matter
    on net as compared to textbooks, as I found this piece
    of writing at this site.

  3. I was very happy to uncover this site. I need to to thank you for your time for this wonderful read!!

    I definitely really liked every little bit of it and i also have you saved to
    fav to see new information in your blog.

Back to top button